## SECTION 2: HOT CHECK PROCEDURE (POWER ON) ### SAFETY REQUIREMENTS ⚠️ **WARNING:** Live electrical components present. Follow all safety procedures: - Wear appropriate PPE (safety glasses, insulated gloves) - Use insulated tools - Verify all cold checks are complete and passed - Ensure proper grounding - Have qualified electrician present for initial power-up ### PRE-STARTUP CHECKLIST - [ ] All cold checks completed and passed - [ ] All field wiring reconnected to proper terminals - [ ] All panel components secured - [ ] Laptop with Eclypse or CCT software ready - [ ] Ethernet Cable and USB network card (if required) available - [ ] Application software file available ### HOT CHECK STEP-BY-STEP INSTRUCTIONS 1. **Initial Power-Up** - Verify all wiring is reconnected per wiring diagrams - Turn ON circuit breaker CB for 120VAC - Verify 120VAC at transformer primary terminals - Check LED power supply (should be lit) - Verify 24VAC output from power supply 2. **Controller Connection** - Connect laptop to controller using available connection - Launch Distech Eclypse or CCT software as applicable - Discover controller on network (Address should appear) - Verify controller firmware version - Check controller status (should show "Online") 3. **Application Software Download** - Open application software file for this project - Verify point schedule matches drawing - Download application to controller - Wait for download to complete (may take several minutes) - Verify download successful (check for errors) - Controller may restart - wait for it to come back online 4. **I/O Module Verification** - In Eclypse or CCT software verify all IOM are online - Check that all I/O points are mapped correctly - Verify no communication errors 5. **Point Testing Procedure** - For each point in the Hot Check Tables: a. Navigate to the point in Eclypse or CCT software b. Observe the current reading displayed c. Verify the reading matches expected value d. For inputs: simulate or verify field condition e. For outputs: command the output and verify field device response f. Record **PASS** if reading/operation is correct g. Record **FAIL** if reading/operation is incorrect h. Document specific values and issues in Notes column