BAS Project Lifecycle - Role Entry/Exit Points & Deliverables

Project Phases Overview

PRE-CONSTRUCTION → PROCUREMENT → INSTALLATION → PROGRAMMING/GRAPHICS → 
COMMISSIONING → CLOSEOUT → WARRANTY/SERVICE

Phase 1: PRE-CONSTRUCTION (Bid → Award → Mobilization)

Project Manager

Entry Point: Project award / contract signing
Activities:

  • Review contract, drawings, specifications, and scope of work
  • Develop project plan (WBS, Gantt chart, critical path)
  • Identify long-lead materials and specialty items
  • Conduct internal project kick-off meeting with all departments
  • Create project budget and establish cost codes in accounting system
  • Schedule external project kick-off meeting with client and GC

Deliverables:

  • Signed contract review and risk assessment
  • Comprehensive project plan with schedule milestones
  • Project budget with labor/material allocations
  • Material procurement list with lead times
  • Kick-off meeting minutes with action items
  • Service Fusion project setup complete

Exit Point: Never exits - stays through warranty period


Warehouse Manager

Entry Point: PM provides material procurement list
Activities:

  • Review material list and check current inventory availability
  • Identify items that need to be ordered
  • Provide lead time estimates to PM
  • Reserve in-stock items for project

Deliverables:

  • Inventory availability report
  • Material procurement recommendations
  • Lead time estimates for all ordered items
  • Preliminary material staging plan

Exit Point: Never fully exits - remains available for expedited needs


Accountant

Entry Point: Contract signing / project setup
Activities:

  • Set up project cost codes in accounting system
  • Establish project billing milestones per contract terms
  • Create project file for invoice and cost tracking
  • Set up client in AR system if new customer

Deliverables:

  • Project cost codes established in GL
  • Billing milestone schedule created
  • Project tracking file initialized
  • WIP reporting format established for this project

Exit Point: Final payment received and project closed (post-warranty)


Phase 2: PROCUREMENT (Material Ordering → Delivery)

PROJECT MANAGER

Activities:

  • Issue purchase orders for materials
  • Track delivery schedules
  • Coordinate with Warehouse Manager on receiving
  • Adjust project schedule based on material arrivals

Deliverables:

  • All POs issued and tracked in Service Fusion
  • Material delivery schedule aligned with installation schedule
  • Communication to field team on material availability

WAREHOUSE MANAGER

Entry Point: POs issued by PM
Activities:

  • Receive and inspect all incoming materials against POs
  • Log materials in inventory system within 4 hours of arrival
  • Notify PM of any discrepancies, damages, or shortages
  • Stage materials for project kit preparation
  • Prepare project material kits 3 days before installation start

Deliverables:

  • All materials received, inspected, and logged (Service Fusion)
  • Discrepancy reports (if any) submitted to PM within 24 hours
  • Project kits staged and ready for field team pickup
  • Material staging checklist signed off

Exit Point: Project kits delivered to field OR final material reconciliation complete


ACCOUNTANT

Activities:

  • Process and code vendor invoices to project
  • Track material costs against budget
  • Provide PM with material cost updates for WIP report

Deliverables:

  • All vendor invoices processed within 48 hours
  • Material costs accurately coded to project
  • Material cost variance report (if over/under budget)

Phase 3: INSTALLATION (Physical Installation of Hardware)

PROJECT MANAGER

Activities:

  • Coordinate installation schedule with GC and other trades
  • Conduct weekly site coordination meetings
  • Monitor installation progress and labor costs
  • Address field issues and RFIs (Requests for Information)
  • Manage any change orders
  • Review daily field reports from installation team

Deliverables:

  • Weekly site coordination meeting minutes
  • Installation progress reports (% complete)
  • RFI responses documented and distributed
  • Change order documentation (if applicable)
  • Updated project schedule with actual progress

INSTALLER

Entry Point: Material kits available and site ready for installation
Activities:

  • Pick up material kits and tools from warehouse
  • Review project blueprints and installation scope
  • Install conduit, raceway, and wire troughs
  • Pull and label all control wiring
  • Mount control panels and field devices (sensors, actuators, etc.)
  • Terminate all wiring at panels and field devices
  • Perform continuity and isolation testing on all wiring
  • Complete daily field reports in Service Fusion

Deliverables:

  • 100% of conduit and raceway installed per drawings
  • 100% of control wiring pulled and labeled
  • All control panels mounted and wired
  • All field devices mounted and wired
  • Continuity test results documented (all circuits passing)
  • Daily field reports with time tracking and materials used
  • Clean and organized installation ready for commissioning
  • Preliminary punch list items noted

Exit Point: Installation complete, passed quality inspection, and handed to Field Specialist

Handoff to Field Specialist:

  • Installation checklist signed off by supervisor
  • All wiring labels match drawing conventions
  • Material usage documented in Service Fusion
  • Any field changes or deviations documented with photos

WAREHOUSE MANAGER

Activities:

  • Provide additional materials as needed (call-backs)
  • Coordinate emergency/expedited shipments
  • Track material usage vs. initial kit

Deliverables:

  • Call-back materials issued and tracked
  • Material usage variance report to PM (if significant)

ACCOUNTANT

Activities:

  • Process weekly labor time from field reports
  • Track installation costs against budget
  • Generate weekly WIP report for PM

Deliverables:

  • Weekly labor costs processed and coded to project
  • WIP report showing installation phase costs vs. budget

Phase 4: PROGRAMMING & GRAPHICS (Control Logic & HMI Development)

PROJECT MANAGER

Activities:

  • Coordinate with Programmer and Graphic Developer on deliverable timelines
  • Review sequences of operation with client (if needed)
  • Monitor programming and graphics progress
  • Schedule integration testing and quality reviews

Deliverables:

  • Programming and graphics schedule confirmed
  • Client approvals on graphic designs (if required by contract)
  • Progress tracking in Service Fusion

NETWORK SPECIALIST

Entry Point: Installation complete, ready for network configuration
Activities:

  • Design network architecture (IP scheme, VLANs, subnetting)
  • Configure and commission managed switches
  • Establish network connectivity for all controllers
  • Coordinate with client IT team for integration
  • Implement secure remote access (VPN, proxies)
  • Harden BAS server and configure firewalls
  • Test all network communication paths

Deliverables:

  • Network architecture diagram
  • IP address list for all devices
  • Managed switch configurations documented
  • VLAN configuration and port mapping
  • Client IT integration sign-off
  • Remote access credentials and documentation
  • Network communication test results (all devices online)
  • Cybersecurity compliance checklist completed

Exit Point: Network fully functional, all devices communicating, documentation complete

Handoff to Programmer & Graphic Developer:

  • Network documentation package delivered
  • All controller IP addresses confirmed and accessible
  • Remote access tested and credentials provided

PROGRAMMER DEVELOPER

Entry Point: Network established, controllers online
Activities:

  • Review mechanical sequences of operation (SOO)
  • Develop control programs for all equipment (VAVs, AHUs, plants, etc.)
  • Implement PID loops, optimal start/stop, scheduling logic
  • Integrate third-party devices (chillers, VFDs, etc.) via BACnet/Modbus
  • Configure alarm and notification systems
  • Test programs on workbench before deployment
  • Deploy programs to field controllers
  • Debug and optimize control logic

Deliverables:

  • Control programs for 100% of equipment per SOO
  • PID loop tuning documentation
  • Third-party device integration maps (BACnet/Modbus objects)
  • Alarm configuration and escalation logic
  • Workbench simulation test results
  • Commented code with block/flow diagrams
  • Program version control and backup files
  • Point-to-point I/O verification checklist

Exit Point: All control programs deployed, tested, and optimized

Handoff to Graphic Developer:

  • Point list with all device names and descriptions
  • Control logic summary for operator reference
  • Critical alarm list for HMI display

GRAPHIC DEVELOPER

Entry Point: Programming complete, all data points available
Activities:

  • Design system schematic graphics (central plants, AHUs, etc.)
  • Create floor plan graphics with equipment placement
  • Link all live data points to visual elements
  • Implement interactive controls (setpoints, overrides) with user permissions
  • Design custom dashboards for KPIs and energy trends
  • Ensure responsive design for desktop and mobile
  • Conduct quality control review (links, branding, consistency)

Deliverables:

  • Complete graphic package for all systems
  • Central plant schematics with live data links
  • Floor plan graphics for all zones/areas
  • Custom dashboards for energy and performance monitoring
  • All data points linked and functional (100% verification)
  • Interactive elements tested and permissions enforced
  • Responsive design verified on multiple devices
  • Graphic quality control checklist completed
  • Operator navigation guide

Exit Point: Graphics deployed, tested, and approved

Handoff to Field Specialist:

  • Graphics package deployed to production server
  • Navigation structure documented
  • User permission matrix documented

ACCOUNTANT

Activities:

  • Process labor costs for programming and graphics work
  • Track specialty labor costs against budget
  • Update WIP report

Deliverables:

  • Programming and graphics labor costs processed
  • WIP report updated with technical deliverables phase

Phase 5: COMMISSIONING (System Testing & Verification)

PROJECT MANAGER

Activities:

  • Schedule commissioning with client and GC
  • Coordinate commissioning team activities
  • Monitor commissioning progress and issue resolution
  • Review commissioning reports and punch list
  • Prepare for substantial completion

Deliverables:

  • Commissioning schedule distributed to all parties
  • Commissioning progress reports
  • Punch list management and tracking
  • Substantial completion documentation

FIELD SPECIALIST

Entry Point: Installation, programming, and graphics complete
Activities:

  • Execute commissioning checklists for all equipment
  • Calibrate all sensors to within 1% accuracy
  • Verify all physical I/O points match programming
  • Test all control sequences through full operational cycles
  • Prove out mechanical operation (valves, dampers, fans)
  • Diagnose and repair any wiring or device faults
  • Conduct system performance verification with client
  • Train building operators on system operation
  • Complete commissioning reports and documentation

Deliverables:

  • Commissioning checklists completed for 100% of equipment
  • Sensor calibration reports with before/after readings
  • I/O verification reports (all points functional)
  • Control sequence verification tests documented
  • Mechanical operation verification (actuators, valves, dampers)
  • Troubleshooting log with all issues and resolutions
  • System performance test results
  • Operator training completion certificates
  • Final punch list items identified and resolved
  • Commissioning report package

Exit Point: System fully commissioned, client acceptance, training complete

Handoff to Project Manager & Client:

  • Signed commissioning acceptance from client
  • Training materials and operator manuals delivered
  • Outstanding punch list items documented (if any)

NETWORK SPECIALIST

Activities (if needed):

  • Troubleshoot any network communication issues during commissioning
  • Optimize network performance
  • Verify remote access functionality

Deliverables:

  • Network performance verification report
  • Communication troubleshooting log (if issues occurred)

PROGRAMMER DEVELOPER

Activities (if needed):

  • Troubleshoot control logic issues found during commissioning
  • Fine-tune PID loops and optimization routines
  • Update programs based on field performance

Deliverables:

  • Final program versions with commissioning optimizations
  • Programming change log (if modifications made)

GRAPHIC DEVELOPER

Activities (if needed):

  • Fix any broken data links discovered during commissioning
  • Adjust graphics based on client feedback
  • Update graphics with any field changes

Deliverables:

  • Final graphics package with any commissioning updates
  • Graphics change log (if modifications made)

ACCOUNTANT

Activities:

  • Process commissioning phase labor and expenses
  • Generate invoice per contract billing milestone (substantial completion)
  • Update WIP report

Deliverables:

  • Commissioning labor costs processed
  • Client invoice generated and distributed
  • Updated WIP report showing project near completion

Phase 6: CLOSEOUT (Final Documentation & Payment)

PROJECT MANAGER

Activities:

  • Compile all closeout documentation
  • Coordinate final punch list completion
  • Submit final invoice to client
  • Conduct project review meeting (lessons learned)
  • Archive project documentation
  • Transition project to service/warranty tracking

Deliverables:

  • Complete As-Built drawings (marked-up from field changes)
  • Final commissioning reports
  • Operation & Maintenance (O&M) manuals
  • Warranty documentation package
  • Training materials and certificates
  • All network, programming, and graphics documentation
  • Final project closeout report
  • Lessons learned documentation
  • Final invoice submitted and payment tracking
  • Project transitioned to service in Service Fusion
  • Client satisfaction survey completed

Exit Point: Final payment received, all documentation delivered, warranty period begins


NETWORK SPECIALIST

Activities:

  • Finalize network documentation package
  • Deliver network credentials and access procedures to client

Deliverables:

  • Final network architecture diagrams (as-built)
  • Complete IP address list
  • Switch configuration files (backup)
  • Remote access procedures and credentials
  • Cybersecurity documentation

Exit Point: Network documentation delivered to PM for closeout package


PROGRAMMER DEVELOPER

Activities:

  • Deliver final control programs and documentation
  • Provide program backup files

Deliverables:

  • Final control program files (all versions and backups)
  • Complete program documentation with comments and diagrams
  • Sequence of operation summary
  • Point list and I/O mapping
  • Alarm list and escalation procedures

Exit Point: Programming documentation delivered to PM for closeout package


GRAPHIC DEVELOPER

Activities:

  • Deliver final graphics package and documentation

Deliverables:

  • Final graphics files (source and deployed versions)
  • Graphic navigation guide
  • User permission matrix
  • Dashboard and trend configuration documentation

Exit Point: Graphics documentation delivered to PM for closeout package


FIELD SPECIALIST

Activities:

  • Complete any final punch list items
  • Deliver field documentation

Deliverables:

  • Final punch list completion verification
  • All daily field reports archived
  • Final calibration reports
  • Operator training materials

Exit Point: All punch list items complete and documented


ACCOUNTANT

Activities:

  • Process final project costs
  • Generate final invoice
  • Close out project in accounting system (after final payment)
  • Conduct final project profitability analysis

Deliverables:

  • Final project costs reconciled
  • Final invoice generated and submitted
  • Final WIP report (project complete)
  • Project profitability analysis (budget vs. actual)
  • Project closed in accounting system

Exit Point: Final payment received and project financially closed


WAREHOUSE MANAGER

Activities:

  • Reconcile material usage vs. material issued
  • Process any material returns to stock
  • Close out project material tracking

Deliverables:

  • Final material usage report
  • Material variance analysis (planned vs. actual)
  • Returned materials logged back to inventory

Exit Point: Material reconciliation complete


Phase 7: WARRANTY / SERVICE (Ongoing Support)

PROJECT MANAGER

Entry Point: Warranty period begins at substantial completion
Activities:

  • Track warranty period expiration
  • Coordinate any warranty service calls
  • Monitor customer satisfaction during warranty
  • Transition to service contract (if applicable)

Deliverables:

  • Warranty period tracking in Service Fusion
  • Warranty service call coordination
  • Service contract proposal (if requested)

Exit Point: Warranty period expires OR service contract begins


SENIOR FIELD OPERATIONS COORDINATOR

Entry Point: Substantial completion / system operational
Activities:

  • Log any warranty service requests
  • Dispatch Field Specialists for warranty issues
  • Track response times and resolution
  • Coordinate with PM on warranty vs. billable work
  • Generate service reports for warranty period

Deliverables:

  • All warranty service calls logged and tracked
  • Warranty service reports (issues, resolutions, response times)
  • Transition to ongoing service contract (if applicable)

Exit Point: Never exits if service contract - continues as ongoing service


FIELD SPECIALIST

Entry Point: Warranty service calls or scheduled preventive maintenance
Activities:

  • Respond to warranty service calls
  • Troubleshoot and resolve system issues
  • Perform preventive maintenance (if under service contract)
  • Document all service activities

Deliverables:

  • Service call reports in Service Fusion
  • Issue resolution documentation
  • System performance verification after service

Exit Point: Service contract ends OR customer chooses not to renew


ACCOUNTANT

Activities:

  • Track warranty costs (labor and materials)
  • Generate service contract invoices (if applicable)
  • Analyze warranty cost vs. project budget

Deliverables:

  • Warranty cost tracking report
  • Service contract invoicing (monthly/quarterly)

Exit Point: Project fully closed and service contract established (or customer lost)


Critical Handoff Points Summary

  1. PM → Warehouse Manager: Material procurement list
  2. Warehouse Manager → Installer: Staged material kits
  3. Installer → Field Specialist: Completed installation with continuity tests
  4. Network Specialist → Programmer: Network online, all controllers accessible
  5. Programmer → Graphic Developer: Point list and control logic documentation
  6. Graphic Developer → Field Specialist: Deployed graphics ready for commissioning
  7. Field Specialist → PM: Signed commissioning acceptance
  8. All Technical Roles → PM: Final documentation for closeout package
  9. PM → Dispatch/Service: Project transition to warranty/service tracking

Service Fusion Workflow Through Lifecycle

Project Setup (PM)

  • Customer and location created
  • Service agreement linked (if applicable)
  • Project number (PO#) established
  • Job category assigned

Procurement (Warehouse Manager)

  • Purchase Orders created in Service Fusion
  • Inventory Orders logged when materials arrive
  • Project kits assembled

Installation (Installer & Field Specialist)

  • Job created with “Scheduled” status
  • Status updates: Dispatched → On the Way → On Site → Started → Completed
  • Drive time and labor time automatically tracked
  • Expenses logged (parking, tolls, supplies)
  • Daily notes and completion notes documented

Programming/Graphics (Specialists)

  • Labor time tracked against project
  • Milestones noted in task list
  • Deliverables documented in completion notes

Commissioning (Field Specialist)

  • Additional visits created if multi-day commissioning
  • Task list marked complete as items verified
  • Final completion notes with client sign-off

Closeout (PM & Accountant)

  • Status changed to “Ready to Close”
  • All labor, materials, and expenses verified
  • Invoice generated in Service Fusion
  • Timesheet reports and expense reports generated
  • Project marked as “Logged” or “Non-Service” as appropriate

Warranty/Service (Dispatch & Field Specialist)

  • New service jobs created linked to original project
  • Service agreement tracking for ongoing maintenance
  • Response time and utilization KPIs monitored

Key Success Factors

  1. Clear handoffs with verification checklists
  2. Real-time documentation in Service Fusion
  3. Proactive communication between roles
  4. Quality control at each phase transition
  5. Comprehensive documentation throughout
  6. Regular PM coordination with all team members